2022 Street Reconstruction Project

Lakeville's 2022 Street Reconstruction Project proposes to reconstruct 6.8 miles of road within the City including reclamation of existing pavement, installation of new pavement section, spot/gutter replacement, spot sidewalk replacement, water system enhancements, and pedestrian curb ramp reconstruction to meet current ADA and storm water management best practices requirements.

Helpful Information

Project Timeline

  • July 13, 2021: Neighborhood meeting
  • August – September 2021: Preliminary engineering
  • October 2021: Finalize feasibility report
  • October 18, 2021: Present feasibility report
  • November 15, 2021: Public hearing
  • November 2021 – January 2022: Prepare plans and specifications
  • February 2022: Open bids
  • April 2022: Assessment hearing
  • April – November 2022: Construction

Neighborhood Meeting

Thank you to the residents who attended the July 13, 2021 neighborhood meeting. Below are the documents that were available at the meeting, and a link to our online comment form to provide feedback to the project team.

Contact Us

If you have any questions regarding the project, contact Steve Ferraro, Public Works Coordinator, at 952-985-2793 or by email.